FACT OF INTEREST
INITIAL OBSERVATION: The Project, initially one (Section: Maçanet - Riudellots), was subsequently divided into two subsections, called: MAÇANET - SILS and SILS - RIUDELLOTS.
YEAR: 2003
|
|
SPECIFICATIONS:
|
|
LENGTH: |
5,66 kms.
|
KIND OF WORK: |
Double track of UIC wide High-Speed Rail Roadway
(Roadway total wide, 14,00 m).
Maximum speed: 350 km/h
Traffic type: Mixed (Passengers and goods)
|
STRUCTURES: |
2 Underpasses and 3 Overpasses.
3 Viaducts:
« Sequía de Sils. viaduct »: 223 m long, 5 spans, 55 m maximum span and 3.122,0 m² area.
«GI-555 highway viaduct »: 178 m long, 7 spans, 30 m maximum span and 2.492,0 m² area.
«Riu d´Esplet »: 99 m long, 3 spans, 41 m maximum span and 1.386,0 m² area.
|
CONTRACT BUDGET (Includes both subsections): 1.139.173,30 € (VAT included)
|
|
ESTIMATED BUDGET TO INVITED TENDERS OF THE WORKS: 36.474.820,37 € (VAT included)
|
|
PERIOD PROVIDED FOR CONSTRUCTION: 20 months. |
|
CLIENT: SPANISH MINISTRY OF PUBLIC WORKS. Railroads Administration. |
|